Phase III Projects
Music, Bldg. 531
Departmental Contact: Mark Somerfield
Music IBW Phase III is to complete the workstation wiring work in 1100, 1200 and 2200 wings (primary construction during the summer months). If there is enough funding available, the plan includes completion of workstation wiring in the Arts and Music Library.
3/13/07 |
Finish design work for wiring 3 wings (1100, 1200, 2200 and Arts/Music Library. |
3/14/07 |
FM reviews document and drawings. |
3/28/07 |
Drawings and specs are reproduced. |
4/5/07 |
First public advertisement. |
4/12/07 |
Second public advertisement. |
4/19/07 |
Pre-bid conference. |
4/27/07 |
Bid opening. |
5/21/07 |
Notice to proceed issued to Blum & Sons. |
6/11/07 |
Procure materials and staging materials. |
6/18/07 |
Layout out cores and coring work commences in 1200 and 2200 wings. |
6/18-7/16/07 |
Conduit and junction box installation in 1200 and 2200 wings. |
7/5/07 |
Painting work begins. |
7/16-7/27/07 |
Data wiring and terminations. |
7/23-8/3/07 |
1100 wing coring, conduit and j-box installation, painting, terminations and testing. |
8/1-9/14/07 |
Alternates: Arts and Music libraries conduit and j-box installation, painting, terminations and testing. |
9/14/07 |
Punch list phase. |
Engineering 1, Bldg. 556
Departmental Contact: Chris La Vino
This is an IBW project for the entire building. Primary construction is to create a structured riser system and build out communications closets, followed by the installation of a cable tray and conduit/j-box system throughout building. Alternate 1 work, pending adequate funding, is to wire the entire building with Cat 5e cabling. Alternate 2 work, pending funding, is to wire 36 labs with one Augmented 6 (Cat 6A) cable.
Cheadle Hall, Bldg. 552
Departmental Contact: LSIT
Pending funding, this project is to create a structured riser distribution system throughout Cheadle Hall. The plan is to gut existing shallow communications closets and create a standard riser system. If funding is available, the second floor may have workstation wiring work included. There is no current funding for this project.